ANALISIS PENGGUNAAN PRECEDENCE DIAGRAMMING METHOD (PDM) PADA KONDISI BERURUTAN (SEQUENTIAL) DITINJAU DARI ASPEK BIAYA DAN WAKTU

Shidqi, Mohammad Narapati (2025) ANALISIS PENGGUNAAN PRECEDENCE DIAGRAMMING METHOD (PDM) PADA KONDISI BERURUTAN (SEQUENTIAL) DITINJAU DARI ASPEK BIAYA DAN WAKTU. Tugas Akhir (S1) - thesis, Universitas Bakrie.

[thumbnail of Cover] Text (Cover)
00. Cover (3).pdf

Download (490kB)
[thumbnail of Bab 1-3] Text (Bab 1-3)
BAB I-III.pdf
Restricted to Registered users only

Download (1MB) | Request a copy
[thumbnail of Bab 4] Text (Bab 4)
BAB IV.pdf
Restricted to Registered users only

Download (474kB) | Request a copy
[thumbnail of Bab 5] Text (Bab 5)
BAB V.pdf
Restricted to Registered users only

Download (276kB) | Request a copy
[thumbnail of Daftar Pustaka] Text (Daftar Pustaka)
BAB Daftar Pustaka.pdf

Download (177kB)

Abstract

ABSTRAK Pembangunan jembatan merupakan salah satu komponen penting dalam mendukung konektivitas dan pertumbuhan ekonomi daerah. Pada proyek pembangunan Jembatan Kretek–Girijati, perencanaan penjadwalan yang efektif diperlukan agar tercapai efisiensi waktu dan biaya. Penelitian ini menganalisis penerapan Precedence Diagramming Method (PDM) pada kondisi berurutan (sequential) untuk mengevaluasi keterkaitan antaraktivitas serta dampaknya terhadap biaya dan waktu proyek. Metode penelitian meliputi studi literatur, pengumpulan data lapangan, serta analisis penjadwalan berdasarkan urutan pekerjaan konstruksi. Hasil penelitian menunjukkan bahwa penerapan PDM mampu mengidentifikasi jalur kritis, memperjelas hubungan ketergantungan aktivitas, serta membantu meminimalkan risiko keterlambatan. Selain itu, metode ini juga mendukung pengendalian biaya melalui optimalisasi alokasi sumber daya sesuai tahapan pekerjaan. Dengan demikian, PDM dapat menjadi alternatif metode penjadwalan yang efektif dalam meningkatkan efisiensi manajemen proyek konstruksi jembatan. Kata kunci: Jembatan, PDM, Sequence, Biaya, Waktu, Penjadwalan Analysis of the Application of the Precedence Diagramming Method (PDM) Under Sequential Conditions in Terms of Cost and Time Case Study: Kretek–Girijati Bridge, Special Region of Yogyakarta Mohammad Narapati Shidqi ABSTRACT Bridge construction plays a crucial role in supporting connectivity and regional economic growth. In the Kretek–Girijati Bridge project, effective scheduling is essential to ensure efficiency in both time and cost. This study analyzes the application of the Precedence Diagramming Method (PDM) under sequential conditions to evaluate activity dependencies and their impact on project cost and duration. The research method consists of literature review, field data collection, and scheduling analysis based on the sequence of construction works. The findings indicate that PDM is effective in identifying critical paths, clarifying activity dependencies, and minimizing the risk of delays. Furthermore, it supports cost control by optimizing resource allocation according to work stages. Therefore, PDM can serve as an effective scheduling approach to enhance project management efficiency in bridge construction. Keywords: Bridge, PDM, Sequence, Cost, Time, Scheduling

Item Type: Thesis (Tugas Akhir (S1) - )
Uncontrolled Keywords: Jembatan, PDM, Sequence, Biaya, Waktu, Penjadwalan
Subjects: Civil Engineering > Bridge Engineering
Civil Engineering > Structural Analysis
Thesis > Thesis (S1)
Divisions: Fakultas Teknik dan Ilmu Komputer > Program Studi Teknik Sipil
Depositing User: Mohammad Narapati Shidqi
Date Deposited: 07 Oct 2025 04:20
Last Modified: 07 Oct 2025 04:20
URI: https://repository.bakrie.ac.id/id/eprint/12814

Actions (login required)

View Item View Item