Analisis Keterlambatan Proyek Pada Pembangunan Gedung, Studi Kasus: Proyek Apartemen ABC Bekasi

Pratiwo, Muhammad Alde (2024) Analisis Keterlambatan Proyek Pada Pembangunan Gedung, Studi Kasus: Proyek Apartemen ABC Bekasi. Tugas Akhir (S1) - thesis, Universitas Bakrie.

[thumbnail of Cover] Text (Cover)
00. Cover.pdf - Accepted Version

Download (1MB)
[thumbnail of BAB I-III] Text (BAB I-III)
01. BAB I-III.pdf - Accepted Version
Restricted to Registered users only

Download (758kB) | Request a copy
[thumbnail of BAB IV] Text (BAB IV)
02. BAB IV.pdf - Accepted Version
Restricted to Registered users only

Download (580kB) | Request a copy
[thumbnail of BAB V] Text (BAB V)
03. BAB V.pdf - Accepted Version
Restricted to Registered users only

Download (195kB) | Request a copy
[thumbnail of BAB Daftar Pustaka] Text (BAB Daftar Pustaka)
04. BAB Daftar Pustaka.pdf - Accepted Version

Download (138kB)
[thumbnail of Halaman Lampiran] Text (Halaman Lampiran)
05. Halaman Lampiran.pdf - Accepted Version
Restricted to Registered users only

Download (663kB) | Request a copy

Abstract

The impact of the COVID-19 pandemic has been felt by all industrial fields, including the construction sector, the effects of this pandemic are very influential in controlling time. In accordance with the health protocol made by the government to prevent the spread of Covid, namely reducing the number of workers in the field which results in an increase in the duration of construction work due to the reduced workforce. This incident greatly disrupted the progress of construction and could cause the project to stop. To prevent this, it is necessary to conduct a more detailed assessment of the risk of delays in construction work caused by the pandemic. So this research was made by analyzing several risk factors that occurred during the implementation of a project that took place in a pandemic. This research was conducted using a qualitative descriptive method and a quantitative approach which was collected by means of a survey through questionnaires distributed in the project environment.

Item Type: Thesis (Tugas Akhir (S1) - )
Uncontrolled Keywords: Project delay, impact of delay
Subjects: Civil Engineering > Building Construction
Civil Engineering
Thesis > Thesis (S1)
Divisions: Fakultas Teknik dan Ilmu Komputer > Program Studi Teknik Sipil
Depositing User: Muhammad Alde Pratiwo
Date Deposited: 16 Jul 2024 08:06
Last Modified: 16 Jul 2024 08:06
URI: https://repository.bakrie.ac.id/id/eprint/9634

Actions (login required)

View Item View Item